This presentation dispels the notion of the elusive as-built critical path and introduce the concept of the algorithmic as-built schedule. As demonstrated at the PMI Global Congress 2010, the as-built critical path is alive and well, left of the data date. With the primacy accorded to the as-built schedule, analysts may welcome the addition of the algorithmic as-built alternative, sourced from the fully progressed update, in revisions of RP 29R-03, the SCL Protocol, and ASCE 67-17.
Presented by: Dr. Gui Ponce de Leon & Dr. Vivek Puri